Docsity
Docsity

Prepare for your exams
Prepare for your exams

Study with the several resources on Docsity


Earn points to download
Earn points to download

Earn points by helping other students or get them with a premium plan


Guidelines and tips
Guidelines and tips

The condominium tower will have 405 units for which a total of 5,000 drawings and plans wi, Exercises of Project Management

The condominium tower will have 405 units for which a total of 5,000 drawings and plans will be needed. On average 60 people will work on the job at the same time and make each a one hour break per day. The project expects no accidents. Since the building is not in the 100-year flood zone, no flooding is expected. Two major repairs (e.g., fixing the roof) are projected to happen every year, while the projected maintenance cost per condo unit is on average $3,000 per year. The success of the project is determined by the following weight factors: Building cost should account for minimum 10%, safety during the construction phase at least 5%, maintenance during the operational phase at 40%, documentation of work at least 3%, and major repairs at least 5%. You

Typology: Exercises

2022/2023

Uploaded on 07/08/2023

megan-pham
megan-pham 🇨🇦

1 document

1 / 3

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
BCEE478/BLDG6571 Assignment 2 (100 points)
Contracts, Project Delivery Methods, Organizations, and QM
Due July 11, 2023
1. Based on the lectures, which is a characteristic of Design-Bid-Build? (5 points)
A. Lump-Sum basis of reimbursement
B. Separate contract for design and construction
C. All of the above
2. "Fast-Tracking" is a characteristic of which of the following delivery method(s)? (No partial
credits; select all that are correct) (5 points)
A. Construction Management at-Risk
B. Integrated Project Delivery
C. Design-Build
D. Design-Bid-Build
E. All of the Above
F. None of the above
3. True or False: Having complete drawings is a characteristic of Design-Bid-Build? (5 points)
A. True
B. False
4. According to the lectures, some owners prefer the CM at-Risk delivery method because of: (5
points)
A. A single point of contracts with designer and contractors
B. The ability to require the constructor to warrant the design
C. The owner's ability to retain control over the design
5. Based on the lecture, which is NOT a characteristic of a Sole Source procurement method? (5
points)
A. Used for specialized services
B. Used for emergency
C. Open Competition
D. Not generally applicable to public projects
pf3

Partial preview of the text

Download The condominium tower will have 405 units for which a total of 5,000 drawings and plans wi and more Exercises Project Management in PDF only on Docsity!

BCEE478/BLDG6571 Assignment 2 (100 points)

Contracts, Project Delivery Methods, Organizations, and QM

Due July 11, 2023

  1. Based on the lectures, which is a characteristic of Design-Bid-Build? ( 5 points) A. Lump-Sum basis of reimbursement B. Separate contract for design and construction C. All of the above
  2. "Fast-Tracking" is a characteristic of which of the following delivery method(s)? (No partial credits; select all that are correct) (5 points)

A. Construction Management at-Risk B. Integrated Project Delivery C. Design-Build D. Design-Bid-Build E. All of the Above F. None of the above

  1. True or False: Having complete drawings is a characteristic of Design-Bid-Build? (5 points)

A. True B. False

  1. According to the lectures, some owners prefer the CM at-Risk delivery method because of: ( points)

A. A single point of contracts with designer and contractors B. The ability to require the constructor to warrant the design C. The owner's ability to retain control over the design

  1. Based on the lecture, which is NOT a characteristic of a Sole Source procurement method? ( points)

A. Used for specialized services B. Used for emergency C. Open Competition D. Not generally applicable to public projects

  1. Who is ultimately responsible for design errors revealed during the construction phase of the DBB project? (5 points)

A. Contractor B. Designer C. Owner D. All of the above

  1. According to the lecture, what is the most common project delivery method used in North America today? (5 points)

A. CM at Risk B. Design-bid-build C. Integrated Project Delivery D. Design-build

  1. Match the contract formats to their characteristics. (5 points)

USE YOUR OWN WORDS to answer all the questions below.

  1. Explain the differences between the duties of project manager and superintendent. (10 points)
  2. Explain the meanings of (1) QM; (2) QC; and (3) QA. (15 points)

Lump-Sum

Cost Plus Fee

Unit Price

Low Bid

Specific rates for materials

A single price

Actual costs plus unknown upper limit

Not a contract format