Bid Schedule for Road Construction Project, Summaries of Construction

A bid schedule for a road construction project, listing 29 items with their respective quantities, unit costs, total costs, and unit costs for the base bid and alternate. The items include various types of lines, markings, and allowances for center lines, edge lines, lane lines, channelizing lines, stop lines, lane arrows, bike symbols, parking lot stall markings, continental crosswalk lines, and discretionary allowances.

What you will learn

  • What is the total cost of the alternate bid for the road construction project?
  • What is the total cost of the base bid for the road construction project?
  • What are the different types of lines and markings included in the bid schedule for the road construction project?

Typology: Summaries

2021/2022

Uploaded on 08/05/2022

nguyen_99
nguyen_99 🇻🇳

4.2

(80)

1K documents

1 / 1

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Item Unit Quantity Unit Cost Total Cost Unit Cost Total Cost
1 103.05
Contract Bond Lump Sum 1.00 $1,400.00 $1,400.00 $1,180.00 $1,180.00
2614
Maintenance of Traffic Lump Sum 1.00 $1,400.00 $1,400.00 $6,000.00 $6,000.00
3624
Mobilization Lump Sum 1.00 $710.94 $710.94 $2,500.00 $2,500.00
4642
Center Line, Type 1 Miles 24.80 $730.00 $18,104.00 $904.00 $22,419.20
5642
Edge Line, 4 inch, Type 1 Miles 39.21 $560.00 $21,957.60 $482.00 $18,899.22
6642
Lane Line, 6 inch, Type 1 Miles 3.96 $370.00 $1,465.20 $429.00 $1,698.84
7643
Center Line, Type 1 Miles 43.89 $1,130.00 $49,595.70 $1,262.00 $55,389.18
8643
Edge Line, 4 inch, Type 1 Miles 76.44 $800.00 $61,152.00 $841.00 $64,286.04
9643
Lane Line, 6 inch, Type 1 Miles 2.91 $520.00 $1,513.20 $524.00 $1,524.84
10 643
Channelizing Line, Type 1 LF 4,648.00 $0.90 $4,183.20 $1.15 $5,345.20
11 643
Stop Line, 24 inch, Type 1 LF 432.00 $5.48 $2,367.36 $6.25 $2,700.00
12 643
Lane Arrow, Single EA 64.00 $100.00 $6,400.00 $182.00 $11,648.00
13 643
Lane Arrow, Double EA 1.00 $205.00 $205.00 $270.00 $270.00
14 643
Bike Symbol Marking with Arrow, 72 inch EA 13.00 $137.00 $1,781.00 $425.00 $5,525.00
15 643
Parking Lot Stall Marking LF 210.00 $5.57 $1,169.70 $2.50 $525.00
16 643
Continental Crosswalk Line LF 896.00 $3.20 $2,867.20 $5.45 $4,883.20
17 643
Dotted Line, 6 inch, White/Yellow LF 350.00 $2.75 $962.50 $2.50 $875.00
18 643
Transverse/Diagonal Line, 24 inch, White, Type 1 LF 854.00 $3.20 $2,732.80 $7.30 $6,234.20
19 643
Transverse/Diagonal Line, 24 inch, Yellow, Type 1 LF 488.00 $3.20 $1,561.60 $7.30 $3,562.40
20 643
Island Marking SF 157.00 $3.00 $471.00 $6.00 $942.00
21 SPEC
Discretionary Allowance Lump Sum 1.00 $11,000.00 $11,000.00 $11,000.00 $11,000.00
22 614
Maintenance of Traffic Lump Sum 1.00 $1,000.00 $1,000.00 $2,800.00 $2,800.00
23 624
Late Mobilization Lump Sum 1.00 $1,000.00 $1,000.00 $1,100.00 $1,100.00
24 642
Center Line, Type 1 Miles 2.00 $1,000.00 $2,000.00 $904.00 $1,808.00
25 642
Edge Line, 4 inch, Type 1 Miles 4.00 $700.00 $2,800.00 $482.00 $1,928.00
26 642
Channelizing Line, Type 1 LF 1,000.00 $1.00 $1,000.00 $0.70 $700.00
27 642
Stop Line, 24 inch, Type 1 LF 20.00 $8.00 $160.00 $5.00 $100.00
28 642
Lane Arrow, Single EA 3.00 $100.00 $300.00 $90.00 $270.00
29 642
Lane Arrow, Double EA 1.00 $200.00 $200.00 $130.00 $130.00
29 Items Base Bid $193,000.00 $227,407.32
Alternate $8,460.00 $8,836.00
The Aero-Mark Company
Oglesby Construction Inc
BID SCHEDULE
ALTERNATE

Partial preview of the text

Download Bid Schedule for Road Construction Project and more Summaries Construction in PDF only on Docsity!

Item Unit Quantity Unit Cost Total Cost Unit Cost Total Cost

The Aero-Mark Company Oglesby Construction Inc BID SCHEDULE

  • 1 103.05 Contract Bond Lump Sum 1.00 $1,400.00 $1,400.00 $1,180.00 $1,180.
  • 2 614 Maintenance of Traffic Lump Sum 1.00 $1,400.00 $1,400.00 $6,000.00 $6,000.
  • 3 624 Mobilization Lump Sum 1.00 $710.94 $710.94 $2,500.00 $2,500.
  • 4 642 Center Line, Type 1 Miles 24.80 $730.00 $18,104.00 $904.00 $22,419.
  • 5 642 Edge Line, 4 inch, Type 1 Miles 39.21 $560.00 $21,957.60 $482.00 $18,899.
  • 6 642 Lane Line, 6 inch, Type 1 Miles 3.96 $370.00 $1,465.20 $429.00 $1,698.
  • 7 643 Center Line, Type 1 Miles 43.89 $1,130.00 $49,595.70 $1,262.00 $55,389.
  • 8 643 Edge Line, 4 inch, Type 1 Miles 76.44 $800.00 $61,152.00 $841.00 $64,286.
  • 9 643 Lane Line, 6 inch, Type 1 Miles 2.91 $520.00 $1,513.20 $524.00 $1,524.
  • 10 643 Channelizing Line, Type 1 LF 4,648.00 $0.90 $4,183.20 $1.15 $5,345.
  • 11 643 Stop Line, 24 inch, Type 1 LF 432.00 $5.48 $2,367.36 $6.25 $2,700.
  • 12 643 Lane Arrow, Single EA 64.00 $100.00 $6,400.00 $182.00 $11,648.
  • 13 643 Lane Arrow, Double EA 1.00 $205.00 $205.00 $270.00 $270.
  • 14 643 Bike Symbol Marking with Arrow, 72 inch EA 13.00 $137.00 $1,781.00 $425.00 $5,525.
  • 15 643 Parking Lot Stall Marking LF 210.00 $5.57 $1,169.70 $2.50 $525.
  • 16 643 Continental Crosswalk Line LF 896.00 $3.20 $2,867.20 $5.45 $4,883.
  • 17 643 Dotted Line, 6 inch, White/Yellow LF 350.00 $2.75 $962.50 $2.50 $875.
  • 18 643 Transverse/Diagonal Line, 24 inch, White, Type 1 LF 854.00 $3.20 $2,732.80 $7.30 $6,234.
  • 19 643 Transverse/Diagonal Line, 24 inch, Yellow, Type 1 LF 488.00 $3.20 $1,561.60 $7.30 $3,562.
  • 20 643 Island Marking SF 157.00 $3.00 $471.00 $6.00 $942.
  • 21 SPEC Discretionary Allowance Lump Sum 1.00 $11,000.00 $11,000.00 $11,000.00 $11,000.
  • 22 614 Maintenance of Traffic Lump Sum 1.00 $1,000.00 $1,000.00 $2,800.00 $2,800.
  • 23 624 Late Mobilization Lump Sum 1.00 $1,000.00 $1,000.00 $1,100.00 $1,100.
  • 24 642 Center Line, Type 1 Miles 2.00 $1,000.00 $2,000.00 $904.00 $1,808.
  • 25 642 Edge Line, 4 inch, Type 1 Miles 4.00 $700.00 $2,800.00 $482.00 $1,928.
  • 26 642 Channelizing Line, Type 1 LF 1,000.00 $1.00 $1,000.00 $0.70 $700.
  • 27 642 Stop Line, 24 inch, Type 1 LF 20.00 $8.00 $160.00 $5.00 $100.
  • 28 642 Lane Arrow, Single EA 3.00 $100.00 $300.00 $90.00 $270.
  • 29 642 Lane Arrow, Double EA 1.00 $200.00 $200.00 $130.00 $130. - 29 Items Base Bid $193,000.00 $227,407. - Alternate $8,460.00 $8,836.